24 questions weighted like the new exam: People 33%, Process 41%, Business Environment 26%.

Before you start

Answer without looking anything up. Wrong answers are where the marks are, so guess rather than skip.

24 questions, timed as if real: 90 seconds each on average.

–:–

Result

The exam you are actually sitting

  • 180 questions, 240 minutes, two optional 10 minute breaks after question 60 and 120.
  • New since 9 July 2026, aligned to PMBOK 8th edition. The 2021 exam retired on 8 July 2026.
  • Domains: People 33%, Process 41%, Business Environment 26%. Business Environment tripled from 8%.
  • Mix: about 40% predictive, 60% agile and hybrid.
  • Item types: multiple choice, multiple response, drag and drop, and graphic interpretation (charts, EV curves, dashboards).
  • Eligibility: 4 year degree plus 36 months leading projects, or no degree plus 60 months, plus 35 contact hours.
  • Fee: PMI’s page currently shows $425 for members; several 2026 sources report $445 member and $675 non-member after an August 2026 increase. Confirm at checkout in your PMI account before you budget.

PMBOK 8 in one screen

6 principles: Adopt a Holistic View, Focus on Value, Embed Quality, Be an Accountable Leader, Integrate Sustainability, Build an Empowered Culture.

7 performance domains: Governance, Scope, Scheduling, Finance, Stakeholder Engagement, Resources, Risk.

5 focus areas: Initiating, Planning, Executing, Monitoring and Controlling, Closing. 40 processes, non prescriptive.

The ones they actually ask

FormulaUse
CV = EV - ACPositive = under budget
SV = EV - PVPositive = ahead of schedule
CPI = EV / ACAbove 1 = efficient
SPI = EV / PVAbove 1 = ahead
EAC = BAC / CPIForecast if trends continue
ETC = EAC - ACMoney still needed
VAC = BAC - EACExpected over or under
PERT = (O + 4M + P) / 6Expected duration
SD = (P - O) / 6Uncertainty of an estimate
EMV = probability x impactRisk value, sum for the project
Channels = n(n-1)/2Communication paths
Float = LS - ESSlack on an activity

Exam tactics that score marks

  • Ask “what delivers value” on every Business Environment item. It is now 26% of the paper.
  • Never pick an option that escalates to the sponsor first. Assess, then act, then escalate.
  • Agile items: the answer is almost always the one that increases feedback and transparency.
  • If two answers look right, choose the one that does the analysis before the action.
  • Personality conflicts: address privately and directly before formal process.